|

FIREBIRD UNVEILS STATE-OF-THE-ART RACE CONTROL TOWER AND NEW STARTING LINE DESIGN
A fixture for the better part of the past four decades
in western
Idaho, Firebird has always taken
a proactive approach at continuing to further enhance
our NHRA Drag Racing facility. Starting in November of
2009 and finishing in April of 2010, an amazing team of
workers helped construct a brand new Race Control Tower
and starting line approach area to kickoff the 2010
Season.
It’s pretty amazing in its own right that the original
tower was in place for such a long period of time.
Looking back to the late 60’s, it’s really amazing that
the ol’ girl (original tower photo below) stood tall and
proud for 42 years. From its meager beginnings the tower
was expanded on a couple different occasions, but in the
end, we had simply outgrown all 304 square feet of the
nostalgic tower.
Strategically designed, the new state-of-the-art, custom
designed facility features an expansive Race Control
split-level room, a fully equipped Media Center, four
offices/suites, Power-Phone-Amp mechanical room,
restrooms, storage rooms, and an assortment of other
accommodations. All together, the structure offers
nearly 3,200 square feet of floor space. Additionally, a
new concrete bulls eye wall and expanded turning radius
was designed and developed in the starting line area to
allow for an enhanced entryway from the unique Firebird
staging lanes.
In combination, a workforce of nearly 100 people and a
multitude of companies were closely involved with the
construction project, which was completed just in time
for the start of Firebird’s 43rd season of NHRA Drag
Racing.
A special ribbon-cutting affair was hosted by the New
Crew during the NAPA Auto Parts Ignitor in early-May. A
wide number of special dignitaries and firms attended
the official unveiling of the Tower. Most noteworthy
were Ada
County
commissioners Rick Yzaguirre and Fred Tilman, Eagle Fire
Chief Dan Friend, Star Fire Deputy Chief Scott Buck,
CSDI General Contractor Jeffrey Langan, and an
assortment of companies & workers tied in with the
multi-faceted construction effort.
We could easily write an entire book on the trials and
tribulations of this very significant effort by everyone
involved. By all accounts, it stands as one of the
single most impressive improvements in track history,
which is a pretty tall statement when you take into
consideration the volume of enhancements we’ve completed
over the past several decades.
Here’s a quick glimpse back at several phases of the
project, basically from the start to the finish. At the
very end of the construction pictorial, we want to take
and thank all those who helped with the tower and
starting line major-league improvement. Unquestionably,
we couldn’t have done it without everyone’s help.
On behalf of the entire New Crew, thank you for
all your assistance!

Original Tower circa 1968 with two Top Fuelers in foreground. |

Last look at the Firebird Tower in November of 2009. |

The old tower was disassembled in December 2009. |

By mid-December, mother nature blanketed the track with 8 inches of snow. |

Two giant heating tents were fabricated to control the ground temperature. |

The last elements of the Tower were torn down in early January 2010. |

Riverstone Concrete poured all the lower foundation walls, some 12’ in height. |

Special Symons concrete forms were utilized from CCS. |

A concrete pumping system was used to move the mud. |

Jay Jones and staff placed hundreds of yards of concrete during the project. |

Cross track look at the start of the project in late-January. |

This starts to provide a perspective of the tall retaining concrete wall. |

To avoid future frost, all footings were placed 30-plus inches below grade. |

The entire first floor features a slab on grade concrete floor. |

Jeffrey Langan and Jack Lunsford with CSDI Construction. |

Structural steel beams were positioned by Riverside Welding. |

To meet key engineering standards, heavy beams helped strengthen the face of the building. |

Jay Jones and plumbing contractor David Chester built knockout boxes. |

One of the best in the trade, Mike Rice Excavation kept busy with his backhoe. |

Foreman Trent Green and estimator Jack Lunsford (left) with CSDI. |

Wood started to give the building some perspective. |

As the roof profile was installed, you could really begin to sense the overall look. |

This is Bill New, electrician Daryl DeGrange and David Chester. |

The tower really gained some momentum in February. |

YMC did a phenomenal job with both the heating and cooling aspect of the sizable project. |

The very talented framing crew were from Phoenix Builders. |

The forest green metal roof complimented all of the existing buildings at Firebird. |

United Roofing was responsible for the roof and soffits. |

Diamond Contractors moved tons of earth throughout the entire task. |

This trio headed up by Mike Rice, left, did extensive dirt work. |
Story continued on Page 2
Return to Firebird Home Page

|